Ethereum's Glamsterdam network upgrade has moved out of December and into 2027. Developers currently see mid-January as the earliest workable mainnet window for ETH, with late January or early February the most realistic target; the exact day has not been set and the timing remains tentative.
What is happening
On the All Core Devs Execution call on Nov. 19, developers reached a rough consensus to proceed with the current Glamsterdam specification unless a viable alternative emerged. Outreach by the Ethereum Foundation to more than 50 affected companies indicated that mid-January is the earliest viable mainnet date without spec changes. Most of those companies said they could patch their contracts by then if the rules stay as written. Deadlines cited by CoinDesk are mid-December for the most serious application problems and Jan. 10 for less urgent ones.
The cause of the delay is a repricing of gas, the fee unit for computation on Ethereum. The base charge for launching a new smart contract rises from 32,000 to 183,600 gas, with separate charges for storing contract code. Security researchers have found about 200 potential problems, and Ethereum Foundation developer Marius van der Wijden estimated that as many as 15,000 programs could be disrupted.
Client teams are not fully aligned. Geth, Nethermind, Reth and ethrex backed proceeding without changes, Besu reluctantly accepted the current approach, and Erigon still wants the rules changed. Some developers argued for spec changes to protect backward compatibility, while others warned that a late change would add risk and delay. If the gas-cost rules do change, the launch could slip further, to April or May 2027.
The next checkpoint is the Nov. 26 call, which is expected to decide whether the Hoodi test network rehearsal goes ahead in the week of Dec. 14. A successful fork on Hoodi, a public testnet that mirrors Ethereum, would set up the mainnet date.
Why it matters
Glamsterdam is a major protocol upgrade, and its gas changes affect how existing smart contracts behave. The extra time is intended to let affected projects fix their code before activation, which reduces the chance of broken applications on mainnet.
For ETH holders and traders, the main points to follow are whether the specification stays unchanged, the outcome of the Nov. 26 call, the Hoodi test timing and any further schedule revisions. Until a mainnet date is formally set, the January 2027 timing should be treated as an estimate rather than a confirmed date.
Key details
- Date: expected around January 2027 (month precision); late January or early February seen as most realistic, with a possible slip to April-May 2027; not confirmed
- Project: Ethereum
- Coins: ETH
- Category: Network Upgrade
- Status: tentative
- Source: Observatorio Blockchain, Cointelegraph (via TradingView), CoinMarketCap Academy, ForkLog, MLQ.ai, Weekly Project Updates (Substack)
UAE